Capital Construction and Maintenance Projects: McNairy Library Boiler Modifications

Capital Construction and Maintenance Projects

McNairy Library Boiler Modifications

Description:

Modification to boilers in McNairy Library and Learning Forum.

Construction Timeframe:

Beginning date:  November 18, 2013 7:00 a.m.
Ending date:  December, 18, 2013 5:00 p.m.

Campus Impact:

The library will remain open, however, there may be some disruptive noise during construction.  Most of the construction will occur between the 5th floor and the roof.

We are sorry for the inconvenience this project may cause and ask that you contact Facilities Management at x3275 or x3282 if you have any questions.  Thank you for your cooperation during this project.