July 13, 2017: Start of content cleanup and copywriting

December 15, 2017: All departments and offices will have access to their content audit reports for review (department and offices will have until Feb. 5 to review)

January 22, 2018: Archive site available (

February 5, 2018: Content cleanup and copy writing complete. Start content migration (content will be frozen). Changes made to current site will not be migrated to new site. All changes will need to be replicated manually to new site.

Early February 2018: Core Team site testing

March 23, 2018: Content migration is complete

March 28, 2018: Website LIVE!

Early April 2018: Cascade user training

June 2018: Archive site ends ( for manual migration