Visual and Performing Arts Center

Capital Construction & Maintenance Projects

Description

Begin construction for the Visual and Performing Arts Center

Construction Timeframe

Beginning Date:    May 10, 2010 @ 7:00 a.m.
Ending Date:    November 16, 2011

Traffic, Parking and Building Impact

The Gilbert Hall parking lot as well as the stone parking lot behind Gaige Hall will no longer be usable during the construction timeframe above. Resident (green parking), faculty/staff and commuter parking will be available at the Parking Garage located at the corner of W. Cottage Ave and N. Prince Street.

A construction entrance will be created along W. Cottage Avenue, which may affect traffic flow along W. Cottage Avenue.

Lyte Auditorium will be closed for the duration of construction.

Activities related to this work will affect parking, traffic and pedestrian flow around Lyte Auditorium.

We are sorry for the inconvenience that these projects may cause and ask that you contact JohnE.Colarussoatx3275orArthurDickinsonatx3282ifyouhaveanyquestions. Thankyou for your cooperation during this project.